F-35 May Never Be Ready for Combat

The F-35’s cannon door causes the plane to pull to one side, reducing the accuracy of the gun. (Photo by http://www.jsf.mil)

 

Testing Report Contradicts Air Force Leadership’s Rosy Pronouncements

The F-35 Joint Strike Fighter program is the most expensive procurement program in Pentagon history. It’s been plagued by schedule delays, gross cost overruns, and a slew of underwhelming performance reviews. Last month the Air Force declared its variant “ready for combat,” and most press reports lauded this as a signal that the program had turned a corner. But a memo issued from the Pentagon’s top testing official, based largely upon the Air Force’s own test data, showed that the Air Force’s declaration was wildly premature.

Dr. Michael Gilmore’s latest memorandum is damning. The F-35 program has derailed to the point where it “is actually not on a path toward success, but instead on a path toward failing to deliver the full Block 3F capabilities for which the Department is paying almost $400 billion.” The 16-page memo, first reported by Tony Capaccio at Bloomberg and then by others, details just how troubled this program is: years behind schedule and failing to deliver even the most basic capabilities taxpayers, and the men and women who will entrust their lives to it, have been told to expect.

The Pentagon’s top testing office warns that the F-35 is in no way ready for combat since it is “not effective and not suitable across the required mission areas and against currently fielded threats.” (Emphasis added) As it stands now, the F-35 would need to run away from combat and have other planes come to its rescue, since it “will need support to locate and avoid modern threats, acquire targets, and engage formations of enemy fighter aircraft due to outstanding performance deficiencies and limited weapons carriage available (i.e., two bombs and two air-to-air missiles).” In several instances, the memo rated the F-35A less capable than the aircraft we already have. Continue reading

F-35 Stealth Fighter Still Has 419 ‘Deficiencies,’ Manager Says

The head of the U.S. Defense Department’s F-35 program said the number of “deficiencies” in the stealth fighter jet’s hardware and software is decreasing but that hundreds of technical challenges remain.

Speaking to reporters last week in his offices in Arlington, Virginia, Air Force Lt. Gen. Christopher Bogdan discussed a range of issues affecting the Pentagon’s biggest weapons program at nearly $400 billion, including the hundreds of lingering deficiency reports, or DRs, known as “technical debt” in acquisition parlance.

There are 419 things that we have yet to decide with the war fighters how we’re going to fix them, whether we’re going to fix them and when we’re going to fix them,” he said. The figure was three times higher a few years ago and “we think the technical debt that we have — the deficiencies that we have — are things that we can handle … within the next two years,” he said. Continue reading

The F-35 Has To Phone Texas Before Taking Off

The U.S. military ran the F-35 Joint Strike Fighter through a series of tests aboard the USS Nimitz super carrier in San Diego in early November. It performed adequately, with one exception — it needed to send its diagnostic data to Lockheed Martin in Fort Worth, Texas, before taking off. If the most recent exercises are any indication, the F-35 may need to phone home every time it sets out on a mission.

First, the good news. The plane flew through its aerial paces well enough and passed a majority of its flight tests. Continue reading